Question: You are the project manager for a large project that spans several of your organizations sites. There are many risks identified throughout the project in
You are the project manager for a large project that spans several of your organization’s sites. There are many risks identified throughout the project in each of the sites of the project. Which one of the following is the most effective method of dealing with the project risks?
A. Create risk owners for each of the project risks.
B. Buy insurance for each of the identified risks.
C. The project manager will need to travel to each of the sites as the risk event is coming into the project schedule.
D. The project manager will need to schedule the risk events so that no risk events overlap at any one time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
