Question: You are the project manager for a scheduled version release of your companys software tracking product. You have linked the WBS and project scope definition

You are the project manager for a scheduled version release of your company’s software tracking product. You have linked the WBS and project scope definition and assigned roles and responsibilities. You might want to display the roles and responsibilities in which of the following?

A. RDM B. PDM C. AOA D. RAM