Question: Youll use the scope management plan to define the project scope statement. Youll also use this plan to build the scope baseline. Which two items
You’ll use the scope management plan to define the project scope statement. You’ll also use this plan to build the scope baseline. Which two items are parts of the scope baseline for the project?
A. The project scope management plan and project charter B. The project scope management plan and the WBS C. The WBS and WBS dictionary D. Time and cost baselines