Question: Given the following AOA network, determine the first activity to be given extra resources by the following priority rules: LO6 (a) Shortest task first (b)
Given the following AOA network, determine the first activity to be given extra resources by the following priority rules: LO6

(a) Shortest task first
(b) Minimum slack first
(c) Most critical followers
(d) Most successors
a c7 5