Question: _______ is a project performance measurement technique that integrates scope, time, and cost data. A. Integrated change control B. Flowcharting C. Earned value management D.
_______ is a project performance measurement technique that integrates scope, time, and cost data.
A. Integrated change control B. Flowcharting C. Earned value management D. Forecasting