Question: When a project manager sends a vendor an RFP, what is he asking for? A. A Request for Proposal so that a decision can be
When a project manager sends a vendor an RFP, what is he asking for?
A. A Request for Proposal so that a decision can be made based on price B. A Request for Proposal so that a decision can be made based on the proposed solution to the WBS C. A Request for Proposal so that a decision can be made based on the proposed solution for the SOW D. A Request for Proposal so that a decision can be made based on the proposed schedule