Question: You are the project manager for your organization. Your current project is similar to a project you finished recently for your organization. You decide to

You are the project manager for your organization. Your current project is similar to a project you finished recently for your organization. You decide to base the current project cost estimate on the previous project. What type of cost estimating are you using in this instance?

A. Analogous B. Parametric C. Definitive D. Rough order of magnitude