Question: Your project involves using a new release of a common software application, but if that release is not available, your team has _____________ plans to
Your project involves using a new release of a common software application, but if that release is not available, your team has _____________ plans to use the current release.
a. contingency
b. fallback
c. reserve
d. mitigation