Question: =11. If activity A is not on the critical path, then the slack for A will equal a. LF - EF. b. EF - ES.
=11. If activity A is not on the critical path, then the slack for A will equal
a. LF - EF.
b. EF - ES.
c. 0.
d. all of the above.