Question: After a control chart (for means) has been developed, samples are taken and the average is computed for each sample. The process could be considered
After a control chart (for means) has been developed, samples are taken and the average is computed for each sample. The process could be considered out of control if
a. one of the sample means is above the upper control limit.
b. one of the sample means is below the lower control limit.
c. five consecutive sample means show a consistent trend
(either increasing or decreasing).
d. all of the above were true.
Step by Step Solution
3.46 Rating (162 Votes )
There are 3 Steps involved in it
d all of the above were true In a control chart for means the ... View full answer