Question: = (b) Formulate an LP problem to crash this project to 10 weeks. Activity Normal Time Crash Time Normal Cost ($) Crash Cost ($) Immediate
=
(b) Formulate an LP problem to crash this project to 10 weeks.
Activity Normal Time Crash Time Normal Cost
($)
Crash Cost
($)
Immediate Predecessors A 3 2 1,000 1,600 —
B 2 1 2,000 2,700 —
C 1 1 300 300 —
D 7 3 1,300 1,600 A E 6 3 850 1,000 B F 2 1 4,000 5,000 C G 4 2 1,500 2,000 D, E