Question: In PERT, slack time equals a. ES + t. b. LS - ES. c. 0. d. EF - ES. e. none of the above.
In PERT, slack time equals
a. ES + t.
b. LS - ES.
c. 0.
d. EF - ES.
e. none of the above.
Step by Step Solution
3.48 Rating (151 Votes )
There are 3 Steps involved in it
In Program Evaluation and Review Technique PERT slack time is defined as the amount of time that an ... View full answer