Question: In PERT, slack time equals a. ES + t. b. LS - ES. c. 0. d. EF - ES. e. none of the above.

In PERT, slack time equals

a. ES + t.

b. LS - ES.

c. 0.

d. EF - ES.

e. none of the above.

Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

In Program Evaluation and Review Technique PERT slack time is defined as the amount of time that an ... View full answer