Question: The critical path is the a. shortest path in a network. b. longest path in a network. c. path with the smallest variance. d. path
The critical path is the
a. shortest path in a network.
b. longest path in a network.
c. path with the smallest variance.
d. path with the largest variance.
e. none of the above.
Step by Step Solution
★★★★★
3.30 Rating (159 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
The critical path is the b longest path in a network The critical path in a project network diagram ... View full answer