1. In a resource-constrained project the second priority in assigning resources is usually given to activities with...
Question:
1. In a resource-constrained project the second priority in assigning resources is usually given to activities with the
a) Smallest duration
b) Least slack
c) Most slack
d) Lowest identification number
e) Highest cost
2. All of the following are kinds of resource constraints except
a) Materials
b) People
c) Equipment
d) Information
e) All of the above are resource constraints
3. Project budgets are developed by time-phasing which of the following?
a) Resource schedules
b) Work packages
c) The network diagram
d) Both A and C are correct
e) A, B, and C are all correct
4. The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk
a) Assessment form
b) Responsibility matrix
c) Scenario assessment
d) Impact assessment
e) Risk severity matrix
5. The demolition of the Seattle Kingdome (Snapshot from Practice) is an example of which of the following?
a) Mitigating
b) Retaining
c) Ignoring
d) Transferring
e) Sharing
Thermodynamics for Engineers
ISBN: ?978-1133112860
1st edition
Authors: Kenneth A. Kroos, Merle C. Potter