Question: 1. In a resource-constrained project the second priority in assigning resources is usually given to activities with the a) Smallest duration b) Least slack c)

1. In a resource-constrained project the second priority in assigning resources is usually given to activities with the

a) Smallest duration

b) Least slack

c) Most slack

d) Lowest identification number

e) Highest cost

2. All of the following are kinds of resource constraints except

a) Materials

b) People

c) Equipment

d) Information

e) All of the above are resource constraints

3. Project budgets are developed by time-phasing which of the following?

a) Resource schedules

b) Work packages

c) The network diagram

d) Both A and C are correct

e) A, B, and C are all correct

4. The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk

a) Assessment form

b) Responsibility matrix

c) Scenario assessment

d) Impact assessment

e) Risk severity matrix

5. The demolition of the Seattle Kingdome (Snapshot from Practice) is an example of which of the following?

a) Mitigating

b) Retaining

c) Ignoring

d) Transferring

e) Sharing

Step by Step Solution

3.46 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Lets address each question stepbystep 1 In a resourceconstrained project the second priority in assi... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!