Question: A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers

A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:

Observation 1 2 3 4 5

Time (Seconds) 84 76 80 84 76

What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of job time is used?


Step by Step Solution

3.47 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the standard time for this task we need to follow these steps Step 1 Calculate the Aver... View full answer