A methods and measurements analyst needs to develop a time standard for a certain task. In a
Fantastic news! We've Found the answer you've been seeking!
Question:
A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:
Observation 1 2 3 4 5
Time (Seconds) 84 76 80 84 76
What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of job time is used?
Related Book For
Posted Date: