a) Use the following information to construct a network diagram using AON notation. Activity Activity time (weeks)
Fantastic news! We've Found the answer you've been seeking!
Question:
a) Use the following information to construct a network diagram using AON notation.
Activity | Activity time (weeks) | Immediate Predecessors(s) |
A | 3 | None |
B | 4 | A |
C | 2 | B |
D | 5 | B |
E | 4 | C |
F | 3 | D |
G | 2 | E,F |
Using the network diagram from problem 1:
b) Calculate the project completion time.
c) Determine which activities are on the critical path.