Question: Complete the performance evaluation report for this subunit. (Enter a variance for each account and select whether the variance is favorable [F] or unfavorable [U].
Complete the performance evaluation report for this subunit. (Enter a variance for each account and select whether the variance is favorable [F] or unfavorable [U]. For any zero variances, enter a 0 in the variance column and then leave the F or U box blank. Enter the variance percent as a percentage rounded to two decimal places, X.XX%.)
| | Actual | Flexible | Flexible Budget | |
| Accel - Subunit X | Results | Budget | Variance (F or U) | |
| Direct Materials | $28,500 | $26,600 | | |
| Direct Labor | 13,600 | 14,400 | | |
| Indirect Labor | 27,000 | 23,900 | | |
| Utilities | 12,500 | 11,600 | | |
| Depreciation | 26,000 | 26,000 | | |
| Repairs and Maintenance | 4,600 | 5,400 | | |
| Total | $112,200 | $107,900 | | |
Step by Step Solution
There are 3 Steps involved in it
To complete the performance evaluation report we will compute the variance for each account by subtracting the flexible budget amount from the actual ... View full answer
Get step-by-step solutions from verified subject matter experts