Question: Draw an AON network using the following data and find the probability of completing the path with the longest expected duration of the in 44
Draw an AON network using the following data and find the probability of completing the path with the longest expected duration of the in 44 days, the official opening date.

Activity 1 2 3 4 5 6 7 8 9 10 11 12 Predecessor 1 1 2 3 4 7 3,7 9 8 10, 11 a 6 0 16 Time (days) 2 7 1 0 2 2 0 m 10 1 20 35 3 10 2 2 2 3 1 2 b 14 2 30 7 4 13 3 2 4 2 3
Step by Step Solution
★★★★★
3.54 Rating (147 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
To solve the problem follow these steps Step 1 Expected Time Calculation The expected time TE for ea... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock