In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which carl betterton's construction company is working:
Activity | Immediate Predecessor(s) | Time (days) |
A | - | 3 |
B | A | 4 |
C | A | 6 |
D | B | 6 |
E | B | 4 |
F | C | 4 |
G | D | 6 |
H | E, F | 8 Carl's team should be able to complete the project in how many days ? the longest path will be ? |