Question: The following data is given for the Stringer Company: Budgeted production 26,000 units Actual production 27,500 units Materials: Standard price per ounce $6.50 Standard ounces
The following data is given for the Stringer Company:
| Budgeted production | 26,000 units |
| Actual production | 27,500 units |
| Materials: | |
| Standard price per ounce | $6.50 |
| Standard ounces per completed unit | 8 |
| Actual ounces purchased and used in production | 228,000 |
| Actual price paid for materials | $1,504,800 |
| Labor: | |
| Standard hourly labor rate | $22 per hour |
| Standard hours allowed per completed unit | 6.6 |
| Actual labor hours worked | 183,000 |
| Actual total labor costs | $4,020,000 |
| Overhead: | |
| Actual and budgeted fixed overhead | $1,029,600 |
| Standard variable overhead rate | $24.50 per standard labor hour |
| Actual variable overhead costs | $4,520,000 |
Overhead is applied on standard labor hours.
The direct materials quantity variance is
a.52,000 unfavorable
b.22,800 favorable
c.22,800 unfavorable
d.52,000 favorable
Step by Step Solution
3.46 Rating (153 Votes )
There are 3 Steps involved in it
To determine the direct materials quantity variance we need to follow a series of steps Step ... View full answer