Question: Waterways Continuing Problem. Direct labor or machine hours may not be the appropriate cost driver for overhead in all areas of manufacturing due to the
Waterways Continuing Problem. Direct labor or machine hours may not be the appropriate cost driver for overhead in all areas of manufacturing due to the complexities of many manufacturing processes. Many companies use activitybased costing (ABC) which uses multiple drivers (items that consume resources) rather than just one driver to apply overhead to their activities. With ABC, a company can use a cost driver that has a direct cause/effect relationship in its applied overhead costs.
For each of these cost pools, what would be the likely activity driver?

Assembling Billing Digging trenches Janitorial Machine maintenance Machine setups Molding Packaging Payroll Plant supervision Product design Purchasing materials Selling Testing Welding Labor Cost or Labor Hours Number of Billings Sent Machine Hours Machine Hours Machine Hours Number of Purchase Orders Cost Per Design or Development Costs or Number of Designs Number of Purchase Orders Number of Sales Calls or Number of Items Sold Number of Tests
Step by Step Solution
3.51 Rating (148 Votes )
There are 3 Steps involved in it
Using activitybased costing ABC we assign overhead costs to products or services based on activities ... View full answer
Get step-by-step solutions from verified subject matter experts