Question: Project L requires an initial outlay at t = 0 of $ 3 5 , 0 0 0 , its expected cash inflows are $

Project L requires an initial outlay at t =0 of $35,000, its expected cash inflows are $10,000 per year for 9 years, and its WACC is 14%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.