Question: Fortes Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on

Fortes Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours.

Inputs Standard Quantity or Hours per Unit of Output Standard Price or Rate
Direct materials 8.0 ounces $ 6.10 per ounce
Direct labor 0.60 hours $ 19.80 per hour
Variable manufacturing overhead 0.60 hours $ 4.40 per hour

The company has reported the following actual results for the product for April:

Actual output 5,600 units
Raw materials purchased 48,200 ounces
Actual cost of raw materials purchased 279,560
Raw materials used in production 44,810 ounces
Actual direct labor-hours 3,150 hours
Actual direct labor cost $ 64,890
Actual variable overhead cost $ 12,915

Required:

1. Compute the materials price variance for April.

2. Compute the materials quantity variance for April.

3. Compute the labor rate variance for April.

4. Compute the labor efficiency variance for April.

5. Compute the variable overhead rate variance for April.

6. Compute the variable overhead efficiency variance for April.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!