Question: Aaron's chairs is in the process of preparing a production cost budget for August. Actual costs in July for 120chairs were: Materials cost $4,780 Labor
Aaron's chairs is in the process of preparing a production cost budget for August. Actual costs in July for 120chairs were:
| Materials cost | $4,780 |
| Labor cost | 2,640 |
| Rent | 1,500 |
| Depreciation | 2,500 |
| Other fixed costs | 3,200 |
Materials and labor are the only variable costs. If production and sales are budgeted to change to140 chairs in August, how much is the expected total variable cost on the August budget?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts