Question: A job order cost sheet for Cullumber Company is shown below. Job No . 9 2 For 2 , 0 0 0 Units Date Direct

A job order cost sheet for Cullumber Company is shown below.
Job No.92
For 2,000 Units
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Beg. bal. Jan. 1
5,900
7,000
4,900
8
7,000
12
8,000
6,000
25
2,400
27
4,000
3,000
15,300
19,000
13,900
Cost of completed job:
Direct materials
$15,300
Direct labor
19.000
Manufacturing overhead
13,900
Total cost
$48,200
Unit cost ($48,200-: 2,000)
$24.10
(a) On the basis of this data, answer the following questions.
(1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job?
Balance in Work in Process Inventory on January 1
$
zoom
Cost of completed job:
Direct materials
$15,300
Direct labor
19.000
Manufacturing overhead
13,900
Total cost
$48,200
Unit cost ($48,200-: 2,000)
$24.10
(2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (Round answers to 0 decimal places, e.g.55%.)
Last year
Current year
Overhead rate
%
%
(b) Prepare summary entries at January 31 to record the current year's transactions pertaining to Job No.92.(List all debit entries before credit entries. Credit account titles are automatically indented when amount is entered. Do not indent manually.)
Date
Account Titles and Explanation
Debit
Credit
Jan. 31
(To record raw materials used)
31
(To record factory labor used)
31
SUPPORT
(To record manufacturing overhead)
31

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!