Question: Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labour-hours. The company based its predetermined overhead rate

Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labour-hours. The company based its predetermined overhead rate for the current year on 53,000 direct labour-hours, total fixedmanufacturing overhead cost of $53,000, and a variable manufacturing overhead rate of $3.20 per direct labour-hour. Recently JobX387 was completed and required 250 direct labour-hours. Required:Calculate the amount of overhead applied to Job X387. (Do not round intermediate calculations.)