Question: 0 : 1 6 : 3 6 Question 6 Risks that have been identified and may or may not happen are referred to as known
::
Question
Risks that have been identified and may or may not happen are referred to as known unknowns, and a should be established to cover them if they are triggered.
Question Select one:
a
Contingency reserve
b
Management reserve
c
Funding reserve
d
Risk buffer
Question
A SWOT analysis is an informationgathering tool that helps increase the range of identified risks by examining strengths, weaknesses, and threats to a project.
Question Select one:
a
Opportunities
b
Options
c
Origins
d
Organizations
Question
Effective reporting systems focus on:
Question Select one:
a
providing complete sets of available data.
b
following the original scope of the project plan.
c
providing the appropriate level of detail in reports to satisfy different levels of managers.
d
managing tradeoffs & addressing risks
Question
Routine, exception, and special analysis are types of
Question Select one:
a
delays
b
meetings
c
reports
d
value
Question
The rule allows no credit for work until the task is complete.
Question Select one:
a
b
c
critical input use
d
proportionality
::
Question
Cost variance is calculated as
Question Select one:
a
EV PV
b
ST AT
c
ST AC
d
EV AC
Question
Consider t Successful Project Monitoring Systems PMS plan, monitor, and facilitate control of:
Question Select one:
a
budgets versus expenses.
b
project activities on PERTCPM diagrams.
c
ontime delivery of products.
d
time versus schedule, cost versus budget, and performance versus planned scope.
Question
Which of the following formulas represents the schedule performance index SPI
Question Select one:
a
EVPV
b
EV PV
c
EV AC
d
EVAC
Question
If your sponsor asks for an estimate as to how much more money your team needs to complete all project work as scheduled, which of the following formulas might you use?
Question Select one:
a
BAC EAC
b
EVPV
c
BAC EVCPI
d
BAC EVEAC AC
Question
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is called
Question Select one:
a
Cost management CM
b
Funding limit reconciliation
c
Triple constraint management
d
Earned value management EVM
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
