Question: 0 3 . Dexter manages a project with many different phases with long durations, and each phase must be done in a sequence. What is
Dexter manages a project with many different phases with long durations, and each phase must be done in a sequence. What is the BEST action that Dexter should take?
a Obtain a project charter for each phase
b Make sure work activities include extra time for team meetings
c Make sure each team member knows how their tasks interact with other tasks
a Make sure the communication plan addresses interdependencies between
the project phases