Question: 0 3 . Dexter manages a project with many different phases with long durations, and each phase must be done in a sequence. What is

03.Dexter manages a project with many different phases with long durations, and each phase must be done in a sequence. What is the BEST action that Dexter should take?
a) Obtain a project charter for each phase
b) Make sure work activities include extra time for team meetings
c) Make sure each team member knows how their tasks interact with other tasks
a) Make sure the communication plan addresses interdependencies between
the project phases