Question: 0 / 4.75 pts Question 3 There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to

0 / 4.75 pts Question 3 There are three
0 / 4.75 pts Question 3 There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station-1 first, then to Station-2, finally to station-3, and then leave the process. There are 4 resources in Station-1, 3 resources in Station-2, and 5 resources in Station-3. The processing time (Tp) at Station-1, Station-2, and Station-3 are 10, 3, 10 minutes, respectively. Compute the hourly capacity of this system. Enter your answer with ONE decimal point Answered 0.2 Fect Answer 24