Question: 0 . 7 units / hr a ) Sanding is the bottleneck. b ) The bottleneck time is 3 3 . 3 3 minutes per

0.7 units/hr
a) Sanding is the bottleneck.
b) The bottleneck time is 33.33 minutes per unit (round your response to two decimal places).
c) The throughput time of the overall system is 156.04 minutes (round your response to two decimal places).
d) If the firm operates 8 hours per day, 20 days per month, the monthly capacity of the manufacturing process is units (enter your response as a whole number).
 0.7 units/hr a) Sanding is the bottleneck. b) The bottleneck time