Question: 0 F Chapter 3 Project Management 7 4 3 EF of A= ES of A + 2 ES of C= EF of A ES of

0 F Chapter 3 Project Management 7 4 3 EF of A= ES of A + 2 ES of C= EF of A ES of A A 2 4 0 2 2 2 H 13 E 15 4 8 DO 0 Start 0 Activity Name 2 4 0 ES EF = Max(2,3) D G B 3 7 CO 3 13 0 3 4 5 LS LF ES = Max(EF of D, EF of E) Activity = Max(8,7) = 8 Duration Figure 3.11 Earliest Start and Earliest Finish Times for Milwaukee Paper For this assignment, above picture describes the Earliest Start and Earliest Finish Times for Milwaukee paper Manufacturing company Inc. Question1. Calculate the latest start and finish times for each activity in Milwaukee Paper's project. (10 marks) Question 2. Calculate the Slack Time and Identifying the Critical Path (s). (10 marks)