Question: 0 . Scenario 4 Part 2 : You have a requirement for a noncommercial amphibious vehicle for Special Forces use. The independent government cost estimate

0.Scenario 4 Part 2:You have a requirement for a noncommercial amphibious vehicle for Special Forces use. The independent government cost estimate is$10,000,000.
How many days must the contract action be publicized prior to issuance of the solicitation?
(2 Points)
10 Days
15 days
30 Days
40 days