Question: 0/2.5 pts rect Question 18 A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the
0/2.5 pts rect Question 18 A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is 45% higher than the base case and assume the worst scenario NPV is 35% lower than the base case. Both the best case scenario and the worst case scenario have a 25% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places. For example, if your answer is 123.45% or 1.2345 then enter as 1.23 in the answer box
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts