Question: 0,5 A 5 0,5 5,12 B 7 Select one: O a. 19 O b. 22 O c. 21 O d. 18 5,10 C 5
0,5 A 5 0,5 5,12 B 7 Select one: O a. 19 O b. 22 O c. 21 O d. 18 5,10 C 5 10,16 F 6 5,11 D 6 What is the late finish time for activity G 16,21 E 5 16,22 G 6 22,26 H 4