08:03 0 OSA Jul23_PGD... NO Vo 4G+ LTE 404 SECTION A Read the article below and...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
08:03 0 OSA Jul23_PGD... NO Vo 4G+ LTE 404 SECTION A Read the article below and answer ALL the questions that follow. [40 MARKS] A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration. Important issues within project scheduling are deadline and cost. Quite often, a specific project must be finished by a certain deadline else penalty costs may incur or customers and or profit may be lost. Therefore, the most important goal of the project manager is to finish the project on the predefined deadline and with minimum cost. This problem is known as a time constrained scheduling problem. When these problems occur in many projects from practice and deadlines must be met, different ways to speed up the project are employed, e.g., by working in overtime, hiring extra resource capacity, changing the mode of activities if it is possible or even outsourcing (parts of) the project. All these options are costly but often unavoidable. With multi-mode projects, two options are considered simultaneously to resolve scheduling problems with predefined deadlines and uncertainty in the duration of activities where deadlines must be met and with the least cost. These are to change the mode of activities with a less costly mode and or hiring extra resource capacity. Thus, the questions arise as to how much, when, and what kind of extra capacity in which mode of activity should be used to meet the deadline against the minimum cost of applying additional resources. Uncertainties may lead to considerable schedule interruptions during the project progress. In fact, the uncertainty may arise from several possible sources such as the activities may take more or less time than originally estimated (activity disruptions), resources may become unavailable (resource disruptions), materials may arrive behind the schedule, ready times and due dates may change, new activities may be added to the project or some existing activities may be removed due to changes in the scope of the project, weather conditions may cause several delays, etc. Some reasons for uncertainty in the duration of activities include incorrect estimation of the task duration and the need to rework according to the inspector's analysis. The proposed problem in this research is unresolved in the literature, especially in the cases where there is uncertainty in the project environment and a robust scheduling is needed. In addition, for projects in practice, it is important to obtain a baseline schedule that responds to changes and uncertainties. This provides the motivation to investigate a solution for the multi-mode project scheduling problem with the given deadline under uncertainty of activity duration. Therefore, the main objective is to obtain a baseline schedule for the proposed problem, which while meeting the existing limitations and having the lowest cost, will be robust against uncertainties. Source: Moradi, H. and Shadrokh, S. 2019. A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration. International Journal of Production Research, 57(10): 3138-3167. Answer ALL the questions in this section. QUESTION 1 (20 Marks) The article makes reference to Time-cost trade-off problems which is one of the most frequent and critical decisions that project managers usually make. Using an appropriate diagram, demonstrate, with reference to the article above, how you would effect the time-cost trade-off on projects with the various uncertainties (or variability), as mentioned in the article, that may impact the project. QUESTION 2 (20 Marks) Utilisation of traditional methods such as critical path method (CPM) by deterministic activity duration fails to overcome the common uncertainties (variabilities), as mentioned in the article, in the project environment. The article prescribes that a "robust scheduling method" be identified. The Critical Chain Project Management (CCPM) method may be considered a "robust scheduling method" to deal with uncertainties (variabilities) in a project. Deliberate on a "deterministic" as opposed to a "probabilistic" schedule and then launch into an expos of how the inadequacies of the CPM may be accommodated by the Critical Chain Project Management (CCPM) method. Be sure to include discussions on the CCPM scheduling process, the time and resource buffers as well as the optimal utilisation of slack calculated from the CPM for use within the CCPM method. = 08:03 0 OSA Jul23_PGD... NO Vo 4G+ LTE 404 SECTION A Read the article below and answer ALL the questions that follow. [40 MARKS] A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration. Important issues within project scheduling are deadline and cost. Quite often, a specific project must be finished by a certain deadline else penalty costs may incur or customers and or profit may be lost. Therefore, the most important goal of the project manager is to finish the project on the predefined deadline and with minimum cost. This problem is known as a time constrained scheduling problem. When these problems occur in many projects from practice and deadlines must be met, different ways to speed up the project are employed, e.g., by working in overtime, hiring extra resource capacity, changing the mode of activities if it is possible or even outsourcing (parts of) the project. All these options are costly but often unavoidable. With multi-mode projects, two options are considered simultaneously to resolve scheduling problems with predefined deadlines and uncertainty in the duration of activities where deadlines must be met and with the least cost. These are to change the mode of activities with a less costly mode and or hiring extra resource capacity. Thus, the questions arise as to how much, when, and what kind of extra capacity in which mode of activity should be used to meet the deadline against the minimum cost of applying additional resources. Uncertainties may lead to considerable schedule interruptions during the project progress. In fact, the uncertainty may arise from several possible sources such as the activities may take more or less time than originally estimated (activity disruptions), resources may become unavailable (resource disruptions), materials may arrive behind the schedule, ready times and due dates may change, new activities may be added to the project or some existing activities may be removed due to changes in the scope of the project, weather conditions may cause several delays, etc. Some reasons for uncertainty in the duration of activities include incorrect estimation of the task duration and the need to rework according to the inspector's analysis. The proposed problem in this research is unresolved in the literature, especially in the cases where there is uncertainty in the project environment and a robust scheduling is needed. In addition, for projects in practice, it is important to obtain a baseline schedule that responds to changes and uncertainties. This provides the motivation to investigate a solution for the multi-mode project scheduling problem with the given deadline under uncertainty of activity duration. Therefore, the main objective is to obtain a baseline schedule for the proposed problem, which while meeting the existing limitations and having the lowest cost, will be robust against uncertainties. Source: Moradi, H. and Shadrokh, S. 2019. A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration. International Journal of Production Research, 57(10): 3138-3167. Answer ALL the questions in this section. QUESTION 1 (20 Marks) The article makes reference to Time-cost trade-off problems which is one of the most frequent and critical decisions that project managers usually make. Using an appropriate diagram, demonstrate, with reference to the article above, how you would effect the time-cost trade-off on projects with the various uncertainties (or variability), as mentioned in the article, that may impact the project. QUESTION 2 (20 Marks) Utilisation of traditional methods such as critical path method (CPM) by deterministic activity duration fails to overcome the common uncertainties (variabilities), as mentioned in the article, in the project environment. The article prescribes that a "robust scheduling method" be identified. The Critical Chain Project Management (CCPM) method may be considered a "robust scheduling method" to deal with uncertainties (variabilities) in a project. Deliberate on a "deterministic" as opposed to a "probabilistic" schedule and then launch into an expos of how the inadequacies of the CPM may be accommodated by the Critical Chain Project Management (CCPM) method. Be sure to include discussions on the CCPM scheduling process, the time and resource buffers as well as the optimal utilisation of slack calculated from the CPM for use within the CCPM method. =
Expert Answer:
Related Book For
Financial Accounting
ISBN: 9780730363217
10th Edition
Authors: John Hoggett, John Medlin, Keryn Chalmers, Claire Beattie, Andreas Hellmann, Jodie Maxfield
Posted Date:
Students also viewed these general management questions
-
Read the article below and answer the questions posed, the compose response should be two to three pages in length. 1. What are 2 major planning failures pre-event at Memorial that led to it becoming...
-
Prepare a personal SWOT analysis (Your personal Strengths and Weaknesses and the external macroeconomic Opportunities and Threats that all of your competitors will assess criteria examples Advantages...
-
Multiple Choice Question 1. The gain on trading securities, reported on the 2013 income statement, is a. $20,000 b. $25,000 c. $45,000 d. $60,000 2. The gain on AFS securities, reported on the 2013...
-
A steady, two-dimensional, incompressible flow field in the xy-plane has a stream function given by = ax 2 + by 2 + cy, where a, b, and c are constants. The expression for the velocity component v...
-
Recall that Life Fitness had estimated \($1,000,000\) of MOH for the year and 62,500 DL hours, resulting in a predetermined MOH rate of \($16/DL\) hour. By the end of the year, the company had...
-
Megley Cheese Company is a small manufacturer of several different cheese products. One of the products is a cheese spread that is sold to retail outlets. Jason Megley must decide how many cases of...
-
1. What is Stock Market Analysis. Explain in Detail? 2. Discuss about Nature and Scope of Stock Market Analysis. 3. Discuss about Basics of Stock Market Analysis. 4. What is Investment? Explain in...
-
Obtain the most recent annual report (or 10-K report) for the year ended 12/31/2022 (filed 2/22/2023) for Boston Beer Co Inc. The easiest way is to use the EDGAR search tools on the SEC.govLinks to...
-
Case: Two months ago, Lisa was honorably discharged from the Air Force where she spent four years training as an airplane mechanic. After discharge, she relocated to take a 40 hour per week...
-
How to modify the following algorithms to display the total number of swap operations. The following algorithms are given: def Algorithm_1(lyst): i = 0 while i < len(lyst) - 1: minIndex = i j = i + 1...
-
How do businesspersons develop the audience profile during the writing process?
-
There are many laws that surround the First Amendment. What rights are guaranteed by the First Amendment?
-
(d) Aina just got her driver license, and she wants to buy a new car cost for RM70,000. She has RM3,000 to invest as a lump sum today. Aina is a conservative investor and she only invests in safe...
-
Read the task The Morey Unit Hostage incident. Write an analysis of the Arizona Department of Corrections Morey unit hostage situation. Make recommendations for how the situation could have been...
-
Compare and contrast debt financing and equity financing as ways of starting a new business. Does one have an overall advantage over the other? What situation is more favorable to the use of debt...
-
Each second, the burning Suns mass (a) increases. (b) remains unchanged. (c) decreases.
-
The Sun contains what percentage of the solar systems mass? (a) about 35% (b) 85% (c) the percentage varies over time (d) over 99%
-
Asteroids orbit (a) the Moon. (b) Earth. (c) the Sun. (d) all of these (e) none of these
Study smarter with the SolutionInn App