Question: 09:10 11 A docs.google.com 1 point Maju Jaya Enterprise has 20 direct workers who work 26 days a month. The production rate is 30 minutes

09:10 11 A docs.google.com 1 point Maju Jaya

09:10 11 A docs.google.com 1 point Maju Jaya Enterprise has 20 direct workers who work 26 days a month. The production rate is 30 minutes per unit with eight (8) working hours per day. The regular labor cost is RM10 per hour. Calculate the regular production rate per month. 8,650 units 8,450 units 8,320 units 8,020 units