Question: # 1 0 . 1 1 1 0 . 1 1 Given the following information, answer the questions about this project: [ [ Activity ,
# Given the following information, answer the questions about this project: ActivityExpected Duration,PredecessorsA days,B days,AC days,AD days,BE days,BF days,CG days,daysH day,E GIH a Draw the network as a Gantt chart. b What is the critical path? Which activities have slack time? c What would happen if activities B and D each took extra days to complete instead of the expected duration? How would the critical path change?