Question: 1 0 A - B - D - E - G A - C - D - F - G A - B - D

10A-B-D-E-G
A-C-D-F-G
A-B-D-F-G
A-C-D-E-G
00:29:35
b. What is the length of time to complete the project?
Number of weeks
c. Which activities have slack, and how much?
B,2 weeks; E,2 weeks.
C,2 weeks; F,3 weeks.
C,1 week; E,2 weeks.
D,1 week; E,2 weeks.