Question: 1 0 A - B - D - E - G A - C - D - F - G A - B - D
::
b What is the length of time to complete the project?
Number of weeks
c Which activities have slack, and how much?
B weeks; E weeks.
C weeks; F weeks.
C week; E weeks.
D week; E weeks.