Question: [ 1 0 marks ] A small software development company has proposed the schedule given below for a client project. [ Recall that we are
marks A small software development company has proposed the schedule given below for a client project.
Recall that we are using the activityonarc formalism. Use the information in the table to construct an activityonarc PERT network diagram before answering the questions below.
a What is the smallest number of days in which the project can be completed? Which activities are critical to ontime completion?
b The company wants to use a person team on this project to keep costs down. Is it possible to complete the project in the minimum time using only a person team?
Please answer the question using the Activity On ARC PERT Network Diagram before answering the questions.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock