Question: 1 0 ) Per the Construction Act, how many days does a contractor have to pay his sub - contractor after he has received payment

10) Per the Construction Act, how many days does a contractor have to pay his sub-contractor after he has received payment (provided that he receives payment within the 28 day deadline)?
A)7 days
B)10 days
C)14 days
D)28 days