Question: ( 1 0 points ) For the following project complete a PERT diagram and determine the normal time to complete, slack for each activity, and

(10 points) For the following project complete a PERT diagram and determine the normal time to complete, slack for each activity, and the critical path.
\table[[Activity,Predecessors,Normal Time],[A,-,8],[B,-,12],[C,-,10],[D,A,B,15],[E,B,C,11],[F,D,12],[G,D,13],[H,E,10],[I,F, G, H,3]]
SHOW ALL WORK
 (10 points) For the following project complete a PERT diagram and