The monthly usage for a component supplied to a medical equipment manufacturing plant is 4718 parts. There are 20 working days in the month, and the effective operating time of the plant is 439 minutes per day. Currently, the defect rate for the component is 3.7%, and the equipment used to produce the part is down for repairs an average of 23 minutes per day. What is the Takt time of this part? Write your answer to two decimal places.