Question: . ( 1 0 Points ) You are forming a team to tackle the production issues in this production line ( see below ) .

.(10 Points) You are forming a team to tackle the production issues in this production line (see below).
The plant operates on 1 shift, 450 mins/day,5 days/week.
Demand for the product is 400 units/day.
Total production time available is 8 hours, with one 0.5 hour lunch break and two 10-minute coffee breaks.
Each process has one operator.
Please place your answer within this spreadsheet.
a.(3 points) Can the given production meet the demand? Why or why not?
b.(3 points) State using bullets where should you focus your efforts? Be brief but precise.
c.(6 points) Calculate the takt time and number of operators required.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!