Question: ( 1 0 pts ) 4 2 , 0 0 0 S . Y . of Road Base course material was to be installed at

(10pts)42,000 S.Y. of Road Base course material was to be installed at a cost of $193,981,200.00 by T.J. Smith Construction Company. The progress of work was evaluated on April 02,2024, and it was found that 27,420 S.Y. of Base Course material has been installed.
a. Determine the percentage completion.
b. Determine the Earned Value of work done.
c. How much is due to the contractor on April 02,2024?
( 1 0 pts ) 4 2 , 0 0 0 S . Y . of Road Base