Question: 1 0 ) Solve the following: DATA GIVEN: Project is: - 3 stories building. - Install 1 6 0 wooden doors on each floor; Production:

10) Solve the following:
DATA GIVEN: Project is:
-3 stories building.
- Install 160 wooden doors on each floor; Production: 1 door per man-hour.
- Number of carpenters 2, one day =8 hours
Find the duration for installing 160 doors.

Step by Step Solution

There are 3 Steps involved in it