Question: 1 0 . Using the data below, schedule the problem in MS Project. Display and print the schedule in a Gantt chart showing the critical

10. Using the data below, schedule the problem in
MS Project. Display and print the schedule in a
Gantt chart showing the critical path and the
predecessors.
WBS ACTIVITY
IMMEDIATE
PREDECESSOR
DURATION
IN WEEKS
1 Operational
definition
1.1 Research
literature
3
1.2 Identify and
define terms
1.11
1.3 Obtain approval
of definition
1.22
2 Target Selection
2.1 Solicit partners
for pilot
2
2.2 Hold brainstorming
meeting
2.12
2.3 Identify characteristics of targets
2.2,3.11
2.4 Obtain approval
of partners
2.3,1.2,3.41
3 Question set
3.1 Identify process
group members
2
3.2 Develop question
set
2.34
3.3 Prototype and
validate
question set
3.23
3.4 Add partners 3.1,2.13
4 Pilot process
4.1 Schedule with
target audience
2.42
4.2 Conduct beta test 3.4,2.42
4.3 Process feedback
from target
audience
4.22
4.4 Conduct pilot 4.32
4.5 Analyze results 4.42

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!