Question: 1 0 ) Why is finding the critical path a necessary part of project management? A ) It separates important activities from unimportant activities B
Why is finding the critical path a necessary part of project management?
A It separates important activities from unimportant activities
B It identifies the shortest possible completion time for the project
C It identifies the longest possible completion time for the project
D It identifies which activities have no slack time
E A and C
F B and D