Question: : 1 04 07 (). : An assembly having the following sequence of activities given along with their predecessor in the table below Activity Predecessor

: 1 04 07 (). : An assembly having the following

: 1 04 07 (). : An assembly having the following sequence of activities given along with their predecessor in the table below Activity Predecessor Duration in weeks 3 B - 4 8 MOO 00 D 5 E C 3 F BE 2 G D 1 4 I F,G The number of nodes with surplus time is: Four nodes Three nodes Two nodes Only one node ols bas "