Question: 1 1 : 3 2 4 GROUP ASSIGNMENT.pdf Question four A new project is to be completed. The following activities need to be completed in

11:32
4
GROUP ASSIGNMENT.pdf
Question four
A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks.
\table[[Activity,\table[[Immediate],[predecessors]],\table[[Optimistic],[time]],\table[[Most],[likely],[time]],\table[[Most],[pessimistic],[time]],Variance],[A,-,2,3,4,0.11111],[B,-,2,4,6,0.44444],[C,A,B,1,2,3,0.11111],[D,B,1,3,5,0.44444],[E,A,2,3,4,0.11111],[F,C,1,4,7,1],[G,E,F,2,2,2,0],[H,D,F,2,5,8,1],[I,G,H,1,3,5,0.44444],[J,I,2,3,4,0.11111]]
You must use two decimal places at all times for expected times when they are not integer (you are not permitted to round off to integers).
(a) Draw the activity network for this problem (6 marks)
(b) Determine the Expected Times. (1 mark)
(c) Determine the activity schedule (ES, EF, LS, and LF) as well as slack. (7 marks)
(d) Determine and state the critical path for this project. (1 mark)
(e) What are the expected time and the variance of the project? (2 marks)
(f) What is the probability that the project is completed in 22 or fewer weeks(1 mark)
(g) What date should be set such that there is a 94% chance of completion within that time? (2 mark
 11:32 4 GROUP ASSIGNMENT.pdf Question four A new project is to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!