Question: 1 1 - 7 Table 1 1 . 8 identifies twenty - six steps in project planning and control. Below is a descrip - tion

11-7 Table 11.8 identifies twenty-six steps in project planning and control. Below is a descrip-
tion of each of the twenty-six steps. Using this information, fill in columns 1 and 2(column 2 is
a group response). After your instructor provides you with column 3, fill in the remainder of the
table.
Develop the linear responsibility chart. This chart identifies the work breakdown
structure and assigns specific authority/responsibility to various individuals as groups
in order to be sure that all WBS elements are accounted for. The linear responsibility
chart can be prepared with either the titles or names of individuals. Assume that this
is prepared after you negotiate for qualified personnel, so that you know either the
names or capabilities of those individuals who will be assigned.
Negotiate for qualified functional personnel. Once the work is decided on, the pro-
ject manager tries to identify the qualifications for the desired personnel. This then
becomes the basis for the negotiation process.
Develop specifications. This is one of the four documents needed to initially define
the requirements of the project. Assume that these are either performance or material
specifications, and are provided to you at the initial planning stage by either the cus-
tomer or the user.
Determine the means for measuring progress. Before the project plan is finalized
and project execution can begin, the project manager must identify the means for
measuring progress; specifically, what is meant by an out-of-tolerance condition and
what are the tolerances/variances/thresholds for each WBS base case element?
Prepare the final report. This is the final report to be prepared at the termination of
the project.
Authorize departments to begin work. This step authorizes departments to begin
the actual execution of the project, not the planning. This step occurs generally
after the project plan has been established, finalized, and perhaps even approved
by the customer or user group. This is the initiation of the work orders for project
implementation.
Develop the work breakdown structure. This is one of the four documents required
for project definition in the early project planning stage. Assume that WBS is con-
structed using a bottom-up approach. In other words, the WBS is constructed from
the logic network (arrow diagram) and checkpoints which will eventually become
the basis for the PERT/CPM charts (see Activity 25).
Close out functional work orders. This is where the project manager tries to prevent
excessive charging to his project by closing out the functional work orders (i.e.,
Activity 6) as work terminates. This includes canceling all work orders except those
needed to administer the termination of the project and the preparation of the final
report.
Develop scope statement and set objectives. This is the statement of work and is one
of the four documents needed in order to identify the requirements of the project.
Usually, the WBS is the structuring of the statement of work.
Develop gross schedule. This is the summary or milestone schedule needed at pro-
ject initiation in order to define the four requirements documents for the project. The
gross schedule includes start and end dates (if known), other major milestones, and
data items.
Develop priorities for each project element. After the base case is identified and
alternative courses of action are considered (i.e., contingency planning), the project
team performs a sensitivity analysis for each element of the WBS. This may require
assigning priorities for each WBS element, and the highest priorities may not neces-
sarily be assigned to elements on the critical path.
Develop alternative courses of action. Once the base case is known and detailed
courses of action (i.e., detailed scheduling) are prepared, project managers conduct
"what if" games to develop possible contingency plans.
 11-7 Table 11.8 identifies twenty-six steps in project planning and control.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!